Local guide

Contractor cash flow in Central Ohio's build-out corridor

Central Ohio, especially New Albany and Licking County, is in a multi-year construction cycle driven by data centers and the Intel campus. For local electrical, mechanical and site contractors, that means more work and bigger contracts, but also longer payment chains and larger cash gaps. This page covers what's being built, what Ohio law says about getting paid, and how to plan the cash.

Data-center subs: see Columbus-area data-center jobs.

What's being built, and when

  • Data centers in New Albany. The City of New Albany says 15 companies have built or announced more than 40 data-center facilities there since 2010 (City of New Albany, accessed 2026-11-17). Meta describes its New Albany campus as a more than $1.5 billion investment (Meta New Albany data center fact sheet, Sept 2026).
  • Meta Prometheus. Phase 1 is live and the campus is expanding (Meta Engineering, Oct 19, 2026). Meta gives no dollar value for it.
  • The wider Columbus market. Cushman & Wakefield's H1 2026 data put about 2,043 MW of data-center capacity under construction in the Columbus market, as reported by Amundson Group and Datacentres.com (data as of H1 2026, accessed 2026-11-17).
  • Microsoft in Licking County. Microsoft's Heath site was in site preparation as of its October 2026 update, with Ames Construction as general contractor and no set timeline for vertical construction (Microsoft local updates, accessed 2026-11-17).
  • Intel Ohio One. Intel reports the first major structural truss installed on the first fab in New Albany (Intel, Oct 2026). Intel's page gives no completion date, so treat any start date for fab work as an estimate.
  • Power. AEP Ohio's data-center tariff, approved by the PUCO in July 2025, requires new data-center customers over 25 MW to pay for a minimum of 85% of their contracted demand (AEP Ohio; POWER magazine, accessed 2026-11-17). Power terms affect which projects go ahead and when.

Timelines in this corridor have moved before. Treat any start date as an estimate until the contract is signed.

The local labor picture

Quarterly employment from the Bureau of Labor Statistics, private sector, Q1 2026 vs Q1 2025 (BLS QCEW, retrieved 2026-11-17; county files by NAICS code):

Segment (NAICS) Licking County Franklin County US
All construction (23)6,309 jobs, +10.4%——
Electrical and wiring contractors (23821)1,811, +105.1%8,399, +14.9%+3.6%
Nonresidential electrical (238212)927, +141.4%7,464, +15.8%+6.4%
Nonresidential plumbing and HVAC (238222)355, +3.2%5,042, +17.3%+3.6%
Site preparation (23891)455, −7.5%801, +27.3%+2.0%
Poured concrete (23811)46, −17.9%460, −16.4%+1.5%
Specialized local freight trucking (484220)240, +22.4%473, −40.4%−0.6%

Sources: BLS Quarterly Census of Employment and Wages, 2026 Q1 industry files for NAICS 23821, 238212, 238222, 23891, 23811 and 484220 (filtered to county FIPS 39089 Licking and 39049 Franklin). Small county segments can swing sharply when a few large employers start or finish work, and QCEW counts jobs by where the employer reports them, so treat the percentages as direction, not precision.

Across Franklin and Licking counties combined, specialty trade contractor employment was up 10.3% in March 2026 from March 2025 (BLS QCEW, Franklin; Licking).

The takeaway: electrical employment in Licking County roughly doubled in a year. Crews are being hired fast, and payroll is the first cost to grow.

What it means for a sub's cash flow

  • Bigger contracts than you're used to. A step up in contract size is a step up in peak cash gap. A $850,000 job can tie up more than half its value in cash before the first check (example below).
  • Longer chains. Large data-center and fab projects often have several tiers between the owner and the trade doing the work. Each one can add a review step and a pay-when-paid clause.
  • Labor competition. When everyone is hiring, wages and overtime go up mid-job, and your bid doesn't.
  • Schedule changes. Delays upstream (power, permits, owner decisions) move your start date, which moves your billing.

Nationally, smaller firms are less likely to have data-center work: 7% of contractors under $100 million in revenue reported it in an April 2026 survey, compared with 42% of larger firms (ABC). Mid-size local subs often come in at the second or third tier.

Ohio payment rules every sub should know

Not legal advice. Check the statute and talk to an Ohio construction attorney. See Ohio retainage rules.

  • 10-day pay-through. A contractor must pay its subs within 10 calendar days of receiving payment from the owner, less contract retainage, or owe 18% annual interest (Ohio Rev. Code § 4113.61, checked 2026-11-17).
  • Public retainage cut to 4% of labor. For public improvement contracts, effective September 30, 2025, retainage is limited to 4% of the labor portion for the whole job, a sub can't be held at a higher rate than the public owner holds from the prime, and retainage is due within 30 days of substantial completion (Ohio Rev. Code § 153.13; OFCC HB 96 guidance, checked 2026-11-17). Private retainage is set by contract.
  • Notice of furnishing within 21 days of first work on many projects, to protect lien rights (§ 1311.05, checked 2026-11-17).
  • Lien affidavit within 75 days of last work on most commercial projects (60 days for one- and two-family homes) (§ 1311.06, checked 2026-11-17).
  • Financing disclosure. Ohio was not on the lists of states with commercial-financing disclosure laws compiled by Venable (Mar 2, 2026) or FunderIntel (Oct 2026) (accessed 2026-11-17). You can still ask any funder, including us, for the total cost in dollars before you sign.

More states and the federal rules: retainage laws by state. When a check is late: the GC slow-pay playbook.

Typical job: a Central Ohio electrical package

A hypothetical second-tier electrical scope on a private commercial project:

Input Value
Contract value$850,000
Duration26 weeks
Materials45% of contract; half bought over the first 3 weeks
Weekly payroll (burdened)$13,500
Billingevery 4 weeks, net 60
Retainage5% (private contract), released 60 days after completion

What the calculator shows:

  • Peak cash gap: about $442,000, in week 12, about 52% of the contract.
  • First check: about $124,000, in week 13.
  • Checks every four weeks after that; the final check and $43,000 of retainage around week 35.
  • Margin: about $117,000.

Run your own Ohio job Open the calculator with this example

Hypothetical example
Peak cash gap$442,000week 12
First check$124,000week 13
Retainage held$43,000released week 35
Margin$117,00013.7% of the contract
Paid out that weekPayment receivedRetainage releasedRunning cash positionYour cash gap

Run your own job

Timing risks to watch

  • Project re-sequencing. Intel's schedule has moved more than once; data-center phases can be accelerated or paused depending on power and tenants.
  • Labor costs mid-job. Build wage growth into long bids.
  • Gear and equipment lead times for electrical and mechanical scopes on large projects.
  • Winter. Site and concrete work slow down; payroll for retained crews doesn't.
  • Tier depth. Ask early who pays whom and when.

Local resources

Crossbrace Capital is not affiliated with any company, utility or agency listed here.

How we can help

Crossbrace Capital is a direct funder for established commercial contractors across the U.S., including Ohio. Availability depends on your state's rules; we'll tell you up front if we can't fund where you are. We fund payroll and materials while pay apps, draws and retainage catch up. We'll ask about your job, your terms and your existing obligations, tell you honestly if funding fits or if a bank line or better terms would serve you better.

Trade pages: electrical · mechanical and HVAC · site-work and utility · Terms: glossary · Industrial work nearby · where the work is · chip fabs

Put your own numbers in

See the most cash your next job will tie up, and the week it hits.

Open the calculatorOr send a request

This guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.