The mobilization cost checklist: what you pay before you can bill

Mobilization is everything you spend to get a job started before you can bill for it. On many jobs it's the first and steepest part of the cash gap. Use this list to price it, ask for a mobilization line item where you can, and put the total into your cash plan before you sign.

Why mobilization is a cash problem

Your first pay app usually goes in at the end of the first billing period, and it gets paid 30 to 60 days after that. Everything you spend in between comes out of your pocket. Mobilization costs land even earlier, sometimes before you're on site.

Some contracts include a mobilization line item that lets you bill part of these costs early. Public owners often pay it in steps tied to progress. Michigan DOT, for example, pays mobilization in increments as earned contract value reaches set percentages (MDOT construction manual, section 150, accessed 2026-11-17). Private contracts vary. Read yours, and ask.

The checklist

Check the items that apply, write a dollar figure next to each, and add them up.

Paperwork and compliance

Materials and deposits

Equipment and site setup

People

Fuel and running costs

Total of the amounts you entered: $0

Nothing you check or type here is sent anywhere. It stays in this browser tab.

Billing for mobilization

Questions to ask before you sign:

  1. Is there a mobilization line item in the schedule of values? How much, and when can it be billed?
  2. Can you bill for materials stored on site? Off site? What proof is required?
  3. Can bond and insurance premiums go on the first pay app?
  4. How often can you bill, and what's the first billing date?
  5. What are the payment terms, and is there a pay-when-paid clause?

Every "yes" moves money earlier on your cash curve.

Turn the list into a number

  1. Add up your checked items. That's your up-front cost.
  2. Open the calculator and put the materials part in as an up-front materials share, and the rest as other costs in the first weeks.
  3. Look at the peak gap and the week it lands.
  4. Compare it with cash and credit available in those weeks.

For more on sizing the whole job, read how much working capital a job needs.

Trade examples: mobilization is a big share of the gap for site-work and utility contractors (equipment and fuel from day one) and concrete contractors (forms, pumps and first pours on a short schedule).

Put your own numbers in

See the most cash your next job will tie up, and the week it hits.

Add your mobilization costs to the calculatorOr send a request

This guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.

Check cash gapCall