On most hyperscale jobs, it isn't you
Much of the major electrical gear on a large data center is "owner-furnished and contractor-installed": "the owner buys the switchgear, UPS, generators and transformers directly, often well before construction, and the electrical contractor installs and commissions them" (Buildermuse, October 2026). If that's your job, your cash problem is payroll and travel, not deposits. See mobilizing a traveling crew.
Deposits are more likely to land on you on colocation and enterprise data centers, utility and substation scopes, and smaller jobs where you supply gear.
How long the wait is
2026 lead-time quotes (Terrapin, updated November 2026):
| Equipment | Lead time |
|---|---|
| Medium-voltage switchgear | 52–80 weeks |
| Pad-mount transformers (to 5 MVA) | 40–65 weeks |
| Substation transformers (5–50 MVA) | 75–110 weeks |
| Diesel generators, 1.5–3 MW | 50–78 weeks |
Wood Mackenzie's survey put large power transformers at an average of 128 weeks and switchgear at 44 weeks in Q2 2025 (reported via Buildermuse). Sources measure different equipment classes, so ranges differ.
How big the deposit is
"Most manufacturers hold a production slot for 10 to 30% of equipment cost" (Terrapin). On $1 million of gear, that's $100,000 to $300,000 paid a year or more before you can bill for installed equipment.
Plan the cash
- Ask whether the owner or GC will buy the gear directly or pay the deposit.
- Negotiate a deposit or stored-materials line in the schedule of values.
- Get the supplier's cancellation and escalation terms in writing.
- Match deposits to milestones you can bill.
- Watch for project pauses before you commit a deposit.
Funding
Crossbrace Capital provides business funding with weekly payments that established subs can use for supplier deposits and materials. Ask any funder what its UCC filing will cover before you sign; we'll explain ours in writing. Costs and terms in writing before you sign.
Frequently asked questions
Do electrical subs on hyperscale jobs pay for switchgear?
Usually not on large hyperscale jobs; the owner often buys it. On other jobs, check your contract.
Can I bill the GC for a deposit?
Only if your contract allows it. Negotiate it before you sign.
Are lead times getting shorter?
Terrapin said MV switchgear lead times "have not meaningfully improved since 2023" as of its 2026 report.
Tell us about the job
If the work is approved and billed, or you need to carry the crew until it is, we'll tell you honestly whether our funding fits.
Send a requestOr run the data-center calculatorThis guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.