What retainage is
Retainage (also called retention) is a percentage of each progress payment that the owner or general contractor holds back until the work is complete. It's security for finishing the job and fixing defects, and it's paid out after completion and closeout.
On a typical commercial job, the owner holds retainage from the GC, and the GC holds the same or a higher percentage from each subcontractor. You earn the money as you do the work, but you don't get it until the end, and often not until well after the end.
How much is typically held (public vs private)
Retainage is typically 5–10% of each payment. Most states cap retainage on public projects at 5%, while percentages on private jobs are often left to the contract (Breva 50-state retainage survey). Many contracts also reduce retainage once the job is 50% complete, but only if the contract says so.
Two practical points:
- Read your subcontract, not just the prime contract. A GC can hold more from you than the owner holds from them, unless your state's law or the contract prevents it.
- Check your state's rules. Caps, release deadlines and interest on late retainage vary by state and by whether the job is public or private. A construction attorney or your state's contractor association can tell you what applies.
Why it hurts more than the percentage suggests
Ten percent sounds small. But on a job with a 10% margin, 10% retainage is your entire profit, held until the end.
In the worked example on our electrical contractors page, a $480,000, 16-week job has a $48,000 margin and $48,000 of retainage. The last progress payment arrives in week 23, but the retainage doesn't come back until around week 25. Until then, you've done all the work, paid all the costs and have nothing to show for it.
And it often takes longer than the contract says: 43% of subcontractors wait more than 90 days for final payment and retainage (Siteline, 2026).
Getting retainage released faster
Most retainage delays come from paperwork and punch lists, not from bad faith. You can control more than you might think:
- Negotiate line-item release when your scope finishes. Early trades, like site work and underground electrical, can otherwise wait for the whole building to finish.
- Ask for a reduction at 50% complete, from 10% to 5%, if the contract doesn't already include one.
- Get closeout documents ready early: as-builts, O&M manuals, warranties, attic stock lists and lien waivers. Start them at 75% complete, not after the last day on site.
- Clear your punch list the same week you receive it, and get written sign-off.
- Track the release date in your receivables like any other invoice, with a follow-up date.
- Know your state's prompt-payment and retainage-release rules and the deadlines they set.
- Send a written demand when the release date passes, citing the contract section and the date the work was accepted.
- Call a construction attorney when a written demand doesn't work, or before your lien or bond-claim deadlines run out.
Planning a job around retainage
- Model it before you bid. Run the job through the cash-gap calculator with your real retainage and release timing. See when your profit actually arrives.
- Don't treat retainage as cash for the next job's payroll. It's money you've earned, but you can't plan payroll around a date you don't control.
- Price it in. If retainage will sit for six months after you finish, the cost of carrying it is part of the job's cost.
If retainage is part of a bigger payroll squeeze, read how to make payroll while you wait on a draw. If your subcontract also has a conditional payment clause, read pay-when-paid vs pay-if-paid.
Can you get funding against retainage? (honest answer)
Some specialty lenders and factors offer products built around retainage receivables. Terms vary widely, and you should compare them by total dollars repaid, like any other offer.
Here's how it works with funding that's based on your deposits: retainage that has been released and deposited shows up in your deposits like any other payment. Retainage that's still being held hasn't been paid to you, so it isn't part of your deposits yet. If retainage is your main gap, the release checklist above is the cheapest place to start.
Checklist
- Read the retainage, reduction and release terms in your subcontract before you sign
- Ask for line-item release and a reduction at 50% complete
- Start closeout documents at 75% complete
- Clear punch lists the same week; get written sign-off
- Put the release date in your receivables with a follow-up date
- Send a written demand when the date passes
- Know your lien and bond-claim deadlines; call an attorney before they run out
- Model retainage in the calculator before you bid the next job
Model retainage on your next job
Enter your retainage percentage and release timing in the calculator to see when your profit actually arrives.
Model retainage in the calculatorOr send a requestThis guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.