How much working capital does a job need?

A job needs enough cash to cover everything you pay out before the job starts paying for itself. That's the peak of your cumulative cash gap. You can estimate it from five inputs: contract value, schedule, materials timing, weekly payroll and billing terms. Retainage decides how long the tail lasts.

The short answer

The working capital a job needs is its peak cash gap: the most money you'll have out of pocket on that job at any one time. It is almost never the job's total cost, and it's usually much larger than the job's profit.

For the default job in our calculator, a $480,000 contract over 16 weeks, the peak gap is about $306,000, in week 10. The job's margin is about $48,000. You need more than six times your profit in cash to get to the first check.

The four things that size the gap

  1. How fast money goes out. Weekly payroll, plus materials, plus equipment and other weekly costs. Front-loaded materials (gear, equipment deposits) make the peak higher and earlier.
  2. How long until the first check. Your billing cycle plus the payment terms. Bill monthly at net 45 and the first check arrives around week 10 or 11. Subcontractors reported waiting 51 days on average to be paid after submitting a pay app (Billd 2026 Market Report, accessed 2026-11-17).
  3. How much of each check you keep back: retainage. At 10%, every check is 10% short until closeout.
  4. How long the job runs. Short jobs can finish before the first check arrives, which means you carry the whole cost (see our concrete contractors page for an example). Long jobs reach a point where checks start paying for new work.

Step by step: a worked example

Our calculator's default job:

Input Value
Contract value$480,000
Duration16 weeks
Materials40% of the contract ($192,000); half bought in the first two weeks
Weekly payroll (burdened)$15,000
Billingevery 4 weeks, net 45
Retainage10%, released 60 days after completion

Step 1: List what goes out each week. Weeks 1–2: $48,000 of materials each week plus $15,000 payroll. Weeks 3–16: the remaining $96,000 of materials spread out (about $6,900 a week) plus $15,000 payroll. Total cost over the job: about $432,000.

Step 2: List what comes in, and when. You bill $120,000 of earned value every 4 weeks. Each check is 90% of that ($108,000) because of retainage. Billed in week 4, paid 45 days later: week 11. Then weeks 15, 19 and 23. Retainage of $48,000 comes around week 25.

Step 3: Track the running total. Add up costs minus receipts week by week. The running total climbs until the first check, then starts to fall.

Step 4: Find the peak. In this example it's about $306,000 in week 10, the week before the first check.

That's the number to plan for. The calculator does steps 1 to 4 for you and draws the curve. → Run your job

Three quick estimates when you don't have time

These are rough. Use the calculator for anything you'll act on.

  1. Weeks-to-first-check method. Average weekly cost × weeks until the first check. For our example: $432,000 ÷ 16 = $27,000 a week; billing every 4 weeks plus 45 days is about 10.4 weeks; $27,000 × 10.4 ≈ $281,000. That's below the real $306,000 because the materials were front-loaded. Add your up-front materials if they're large.
  2. Share-of-contract method. On monthly billing with net 45 to 60 terms, the peak landed between about half and most of the contract value in the examples on our industry pages (computed: from 51% (plumbing) to 86% (concrete); all inputs assumed). Treat it as a sanity check only.
  3. Surety rule of thumb (for your whole backlog, not one job). Sureties look at working capital when they set bonding capacity. One commonly cited benchmark is working capital of about 10% of backlog (Fintruction, citing Old Republic Surety, accessed 2026-11-17); another source cites 5–10% of cost to complete (Construction CFO, accessed 2026-11-17). Requirements vary by surety. That's a minimum for your balance sheet, not the cash a single job ties up.

Across all your jobs: the backlog view

One job's gap is only part of the picture. If you're running three jobs, their curves overlap. A new job's peak can land in the same weeks as another job's retainage wait.

A simple way to see it: run each job through the calculator, then line up the weekly totals in a spreadsheet. The highest combined week is your company-level peak. Compare it with:

  • cash in the bank,
  • your available line of credit,
  • checks you're confident are coming in that window.

If the combined peak is bigger than all three, you have a decision to make before you sign the next job.

Ways to shrink the number

Before you finance a gap, try to make it smaller. Each of these changes an input in the calculator:

  • Bill more often. Two-week billing instead of monthly can cut the peak sharply. On our concrete example it cut the gap by about $169,000 (computed).
  • Negotiate terms. Net 30 instead of net 45 or 60.
  • Bill stored materials. If the contract allows billing for materials delivered and stored, gear and equipment come back sooner.
  • Ask for a mobilization line item. See the mobilization cost checklist.
  • Negotiate retainage down or out. Many states cap it, especially on public work: retainage laws by state.
  • Use supplier terms. 30 or 60 days from your supplier shifts materials closer to your first check.

What's left after that is the gap you actually need to fund, from cash, a bank line, or a business funding product. Compare them in advance vs. line of credit vs. factoring.

Trade-specific examples: electrical contractors (gear up front) and mechanical and HVAC contractors (long closeout).

What to do this week

  1. Pick the job you're about to sign or start.
  2. Put its numbers in the calculator.
  3. Write down the peak and the week it lands.
  4. Check it against cash, credit and incoming checks for those weeks.
  5. If there's a shortfall, work through the list above before you look at funding.

Terms used on this page are defined in our contractor cash-flow glossary.

Put your own numbers in

See the most cash your next job will tie up, and the week it hits.

Run your job in the calculatorOr send a request

This guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.