Not legal advice. This page summarizes selected statutes for general information. Laws change, many have exceptions and thresholds we don't list, and your contract matters. Check the linked statute and talk to a construction attorney before you rely on any of it.
How to read this page
- Public means a contract with a government owner (state, city, school district). Private means everything else.
- Cap is the most an owner (and usually a GC, from you) can hold. Some caps are per payment, some are a share of the whole contract. They are not the same thing; see below.
- Release is when the owner has to pay it out.
- Pass-through means the rule also limits what the GC can hold from subs, or how fast the GC must pay subs once the owner pays.
- "Checked" is the date we last read the statute at the linked URL.
State table
| State | Public jobs | Private jobs | Pass-through and timing for subs | Statute (checked 2026-11-17) |
|---|---|---|---|---|
| California | Not covered on this page yet | For private contracts entered on or after Jan 1, 2026: retention may not exceed 5% of any payment, and total retention may not exceed 5% of the contract price; a sub's retention can't exceed the percentage in the owner-GC contract; exceptions apply (for example, some residential projects and bond situations) | Sub retention limited to the upstream percentage | Cal. Civ. Code § 8811 |
| Florida | 5% of each progress payment, for public contracts over $200,000 under § 255.078 | Not covered on this page yet | See statute | Fla. Stat. § 255.078 |
| Georgia | For contracts from July 1, 2022: no more than 5% of each progress payment | Owner may retain no more than the percentage stated in the contract | Public: contractor pays subs their share within 10 days of receiving payment | O.C.G.A. § 13-10-80; § 13-11-5 |
| Indiana | Local public works over $200,000: either 6% of each payment until the job is 50% complete and nothing further, or 3% until substantial completion; held in escrow | Not covered on this page yet | See statute | Ind. Code § 36-1-12-14 |
| Louisiana | Up to 10% on contracts under $500,000; up to 5% on contracts of $500,000 or more; held until 45 days after recorded acceptance (subject to liens) | Not covered here | Private: contractor must pay subs no later than the 7th day after receiving payment | La. R.S. 38:2248; La. R.S. 9:2784; Legislative Auditor FAQ |
| New York | Generally 5% on state contracts, with exceptions | Owner may retain no more than 5% of the contract sum; GCs and subs no more than 5% and never more than the owner actually holds; release within 30 days of final approval; coverage limits apply | Late release of retainage carries interest under the article | N.Y. Gen. Bus. Law § 756-c; N.Y. State Fin. Law § 139-f |
| Ohio | Effective Sept 30, 2025: no more than 4% of the labor portion over the whole job (previously 8% on the first half); subs can't be held at a higher rate than the public owner holds from the prime; release within 30 days of substantial completion, less what's needed to finish | Not covered here | Contractor pays subs within 10 calendar days of receiving the owner's payment (less contract retainage), or owes 18% a year interest | Ohio Rev. Code § 153.13; OFCC HB 96 guidance; § 4113.61 |
| Texas | Public contracts under $5 million: up to 10%; $5 million or more: up to 5% (dams excepted) | Owner must retain 10% of the contract price during the work and for 30 days after completion, to protect lien claimants | See statutes | Tex. Gov't Code § 2252.032; Tex. Prop. Code § 53.101 |
Want a state we haven't listed? For a broader, secondary overview of all 50 states, see the Breva survey (as of June 16, 2026); always confirm against the statute.
Federal jobs
- Retainage is the exception, not the rule. Under the Federal Acquisition Regulation, the contracting officer may retain part of a progress payment only when satisfactory progress hasn't been made, and generally no more than 10% (FAR 32.103, checked 2026-11-17).
- Prompt pay to subs. Prime contractors must pay subs for satisfactory work within 7 days of receiving payment from the agency (31 U.S.C. § 3905, checked 2026-11-17).
- Payment-bond claims. A sub with no direct contract with the prime must give notice within 90 days of its last work to bring a Miller Act claim (40 U.S.C. § 3133, checked 2026-11-17).
What changed recently
- Ohio, Sept 30, 2025: public retainage cut to 4% of labor for the whole job, with no escrow requirement (OFCC guidance).
- California, Jan 1, 2026: private retention capped at 5% for new contracts (Civ. Code § 8811).
- Georgia, July 1, 2022: public retainage cut to 5% of each payment (§ 13-10-80).
- New York, December 2025: reported changes to private-project retainage rules (Breva). The NYSenate.gov text we linked showed a 2023 revision when checked; confirm the current text before relying on it.
Per-payment cap vs contract-sum cap
A 5% cap on each payment and a 5% cap on the total contract can produce different results if the contract also lets the owner keep holding retainage after the job is half done, or hold extra for specific problems. California's private rule has both. Read which one your state uses, and whether your contract asks for more than the law allows. A contract term that conflicts with a statutory cap may not be enforceable, but that's a question for your attorney.
How to use the law on your next job
- Before you bid: look up the cap for that state and job type. If the contract asks for 10% and the law caps it at 5%, raise it in negotiation.
- Before you sign: check the release trigger (substantial completion, final completion, owner acceptance) and whether the GC must pass retainage through when the owner releases it.
- In your cash plan: put the actual retainage percentage and release timing into the calculator. On a $720,000 job, 10% is $72,000 that comes back weeks after you finish (see our electrical example).
- At closeout: send a written request for retainage the day you hit the release trigger. Track the deadline. If it passes, see the GC slow-pay playbook.
Trade context: retainage tends to hurt most where it's held longest, such as mechanical and HVAC jobs that wait on commissioning, and on public site-work and utility jobs. For the cash-flow side, read retainage and your cash flow. Terms are defined in our glossary.
Working in Ohio? See our Central Ohio contractor cash-flow guide (link only if that page is enabled).
Sources and review log
| State or rule | Source | Last checked |
|---|---|---|
| California private | https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=CIV§ionNum=8811 | 2026-11-17 |
| Florida public | https://leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html | 2026-11-17 |
| Georgia public / private | https://law.justia.com/codes/georgia/title-13/chapter-10/article-2/section-13-10-80/ ; https://law.justia.com/codes/georgia/2022/title-13/chapter-11/section-13-11-5/ | 2026-11-17 |
| Indiana local public | https://law.justia.com/codes/indiana/title-36/article-1/chapter-12/section-36-1-12-14/ | 2026-11-17 |
| Louisiana public / private pay-through | https://legis.la.gov/Legis/Law.aspx?d=94968 ; https://legis.la.gov/legis/Law.aspx?d=107211 | 2026-11-17 |
| New York private / public | https://www.nysenate.gov/legislation/laws/GBS/756-C ; https://www.nysenate.gov/legislation/laws/STF/139-F | 2026-11-17 |
| Ohio public / prompt pay | https://codes.ohio.gov/ohio-revised-code/section-153.13 ; https://dam.assets.ohio.gov/image/upload/ofcc.ohio.gov/Portals/0/Documents/HB96_Guidance.pdf ; https://codes.ohio.gov/ohio-revised-code/section-4113.61 | 2026-11-17 |
| Texas public / private | https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2252.htm ; https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm | 2026-11-17 |
| Federal | https://www.acquisition.gov/far/32.103 ; https://www.law.cornell.edu/uscode/text/31/3905 ; https://www.law.cornell.edu/uscode/text/40/3133 | 2026-11-17 |
| 50-state overview (secondary) | https://www.breva.ai/blog/50-state-retainage-cap-survey | as of 2026-06-16 |
Put your own numbers in
See the most cash your next job will tie up, and the week it hits.
Model retainage in the calculatorOr send a requestThis guide is general information, not legal, tax or financial advice. Talk to your CPA or attorney about your situation.