For commercial plumbing and piping contractors

Working capital for commercial plumbing contractors

You put the underground in during month one, rough-in by month three, and you won't set a fixture until the drywall's done. Crossbrace Capital helps established commercial plumbers carry pipe, fixtures and crews between inspections and pay apps, with a plain-dollar cost disclosure in states that require one.

5 taps. No contact details to see your number.

Check your cash gap

Up to 5 taps to an estimate. No contact details needed to see it.

Let's size the cash gap on a job. 5 taps at most, and you don't need to give contact details to see the number. Nothing is sent to us until you press Send at the end.

Start

Prefer a regular form?

  • Commercial contractors onlyWe don't fund consumers or household needs
  • No SSN to startThe first step asks about your business and the job
  • SMS consent is never precheckedYou choose whether we text you
  • Plain-dollar disclosureWritten cost disclosure where state law requires one

The plumbing job in three phases

A commercial plumbing scope is usually three jobs on one contract, separated by other trades' work:

  • Underground

    Sanitary, storm and water under the slab. Early, fast, inspected before the concrete crew can pour.

  • Rough-in

    Waste, vent and supply piping in the walls and ceilings. Inspected and pressure-tested before the walls close.

  • Trim and finish

    Fixtures, water heaters, final connections, often months later, after drywall, paint and ceilings.

Between rough-in and trim there's usually a quiet stretch where your crew moves to other jobs but your billing slows down, and the fixtures for trim still need to be ordered and paid for. That's where plumbing cash gets tight.

Typical job: a $380,000 plumbing scope

A hypothetical plumbing package for a two-story medical office:

  • $380,000 contract over 20 weeks
  • Materials at 35% of the contract; 40% of that bought for underground and rough-in in the first two weeks
  • $10,000 a week in burdened payroll
  • Pay app every 4 weeks, net 45, 10% retainage released 60 days after completion

What the calculator shows:

  • Peak cash gap: about $193,000, in week 10.
  • First check: about $68,000, in week 11.
  • Retainage: $38,000, around week 29, two months after you finish.
  • Margin: about $47,000 (12.4%). The peak gap is about four times the profit.

If the fixture package lands in one order before trim, add it as an up-front cost in the calculator; it creates a second, smaller hump late in the job.

Run your own job Open the calculator with this example

Hypothetical example
Peak cash gap$193,000week 10
First check$68,000week 11
Retainage held$38,000released week 29
Margin$47,00012.4% of the contract
Paid out that weekPayment receivedRetainage releasedRunning cash positionYour cash gap

Run your own job

On a data-center job? See fire-protection subs and mechanical and piping subs on data-center work.

Your pay timeline

Example timeline: plumbing jobHypothetical $380,000, 20-week job billed every 4 weeks on 45-day terms with 10% retainage. Peak gap about $193,000 in week 10.
  1. Week 0Underground startsPipe, fittings, crew
  2. Week 4You billPay app for rough-in
  3. Week 10GC gets paidOwner pays the GC
  4. Week 11You get paidLess retainage
  5. Week 29Retainage releasedAfter closeout
Week-by-week table
Phase Inspection or gate Billing Cash
Underground (weeks 1–4) Underground inspection before pour Billed in pay app 1 (week 4) Pipe and labor out; nothing in
Rough-in (weeks 5–12) Rough-in and pressure tests before cover Pay apps 2–3 First check around week 11
Dead zone (weeks 12–16) Waiting on drywall and ceilings Little to bill Fixture order goes in
Trim (weeks 16–20) Final plumbing inspection; certificate of occupancy depends on it Final pay app Fixtures and labor out
Closeout Punch list, as-builts, warranties Retainage requested Retainage around week 29

A failed inspection doesn't just cost rework labor. It can delay the next trade, and the work can't be billed as complete until it passes.

Inspections, fixtures and the trim-out wait

  • Fixture packages

    Specified fixtures and water heaters can be expensive and lead-time sensitive. Suppliers may want payment before the trim phase you can bill for.

  • Pressure-test and inspection failures

    Rework hits payroll; the billing waits for the re-inspection.

  • Other trades' delays

    Trim depends on drywall, paint and ceilings. If the GC's schedule slips, your last 20–30% of billing slips with it.

  • Weekly payroll, monthly billing

    Your crew is paid every Friday; the pay app goes in once a month. See making payroll before a draw.

  • Service vs. new construction

    Shops that run both have a fast-paying service book and a slow-paying project book. A big project can drain the account the service side depends on.

Nationally, nonresidential plumbing and HVAC contractors employed about 646,000 people in Q1 2026, up 3.6% year over year (BLS QCEW, NAICS 238222, 2026 Q1, retrieved 2026-11-17).

Retainage rules differ by state and by public versus private work: retainage laws by state.

Questions we ask plumbing contractors

Send a request

  1. What phase is the job in, and when are the inspections scheduled?
  2. When does the fixture package need to be ordered and paid for?
  3. What's your billing schedule and retainage, and does the GC bill stored materials?
  4. How much of your revenue is service work versus new construction?
  5. How have your business deposits looked over recent months?
  6. Any existing advances or loans with daily or weekly payments? If so, how do those payments line up with your monthly checks? (See daily vs. weekly remittance.)

Fit and no-fit

Usually a fit

Established commercial plumbing contractors with steady deposits, signed work and a gap that ends with a known pay app or retainage release. One year in business is our only published minimum, and existing advances don't rule you out.

Usually not a fit

Residential service-only shops with no project gap, a job with a disputed inspection or change order that may not resolve, or a need a supplier credit line would cover at lower cost.

Product note: Crossbrace Capital is a direct funder. We fund plumbing contractors two ways: business funding repaid on a weekly or daily schedule (for contractors, we lead with weekly), and receivables financing against invoices and pay apps you've already billed. Costs and terms depend on your business and are set out in writing before you sign.

FAQ

Can I use funding to buy a fixture package before trim?

If materials for signed work are an approved use, yes. Ask your supplier about terms first; 30 or 60 days of supplier credit may be cheaper.

My job has a three-month gap between rough-in and trim. Does that matter?

It matters for timing. We'll ask when each phase bills so the payment schedule doesn't land in the stretch where nothing's coming in.

I do both service and commercial work. Which deposits do you look at?

All of your business deposits. A steady service book is part of the picture.

Do I need to give my SSN to start?

No.

What does it cost?

It depends on your business, amount and term. Ask for the total cost in dollars before you sign. Required disclosures are provided in states that require them.

Know your gap. Then talk to us.