Free contractor tool
How much cash will this job tie up?
Enter a few numbers about the job. You'll see, week by week, how much of your own cash goes out before the customer's money comes in, the most you'll be out at one time, and the week it hits.
Free. No email needed. Nothing you enter is stored unless you choose to send us a request.
Calculator
Free. No email needed. Nothing you enter is stored.Prefilled from the numbers you entered. Change any number to match your job.
Your result
$306,000
You'll be out about $306,000 at the most, in week 10. Your first payment of about $108,000 arrives in week 11.
On this job, you'd pay out $306,000 before the first check arrives. Your margin on the job is $48,000 (10% of the contract), which is about the same as or less than the retainage being held, so you won't see the profit until retainage is released.
Show the week-by-week table
| Week | Paid out | Received | Running total |
|---|---|---|---|
| 1 | $69,000 | – | -$69,000 |
| 2 | $69,000 | – | -$138,000 |
| 3 | $21,000 | – | -$159,000 |
| 4 | $21,000 | – | -$180,000 |
| 5 | $21,000 | – | -$201,000 |
| 6 | $21,000 | – | -$222,000 |
| 7 | $21,000 | – | -$243,000 |
| 8 | $21,000 | – | -$264,000 |
| 9 | $21,000 | – | -$285,000 |
| 10 | $21,000 | – | -$306,000 |
| 11 | $21,000 | $108,000 | -$219,000 |
| 12 | $21,000 | – | -$240,000 |
| 13 | $21,000 | – | -$261,000 |
| 14 | $21,000 | – | -$282,000 |
| 15 | $21,000 | $108,000 | -$195,000 |
| 16 | $21,000 | – | -$216,000 |
| 17 | – | – | -$216,000 |
| 18 | – | – | -$216,000 |
| 19 | – | $108,000 | -$108,000 |
| 20 | – | – | -$108,000 |
| 21 | – | – | -$108,000 |
| 22 | – | – | -$108,000 |
| 23 | – | $108,000 | $0 |
| 24 | – | – | $0 |
| 25 | – | $48,000 | $48,000 |
| 26 | – | – | $48,000 |
| 27 | – | – | $48,000 |
| 28 | – | – | $48,000 |
| 29 | – | – | $48,000 |
| 30 | – | – | $48,000 |
| 31 | – | – | $48,000 |
| 32 | – | – | $48,000 |
| 33 | – | – | $48,000 |
| 34 | – | – | $48,000 |
| 35 | – | – | $48,000 |
| 36 | – | – | $48,000 |
| 37 | – | – | $48,000 |
This is an estimate based on the numbers you entered and simple assumptions (even progress, costs paid when incurred, payment on the stated terms). It isn't financial advice and it isn't a funding offer.
Working a data-center job? Try the data-center version with trade presets.
How to read your result
- Peak cash gap is the most of your own money tied up in the job at once. That's the number to plan for, not the contract value.
- When it hits matters. A gap that peaks in week 10 needs cash in place by week 8 or 9, not when you notice the account is low.
- Retainage is the tail. Even after the last progress payment, part of your money, often your profit, is still held. More in retainage and your cash flow.
- Run it twice. Try your normal terms, then add 30 days to see what a slow-paying GC does to the gap.
How the math works
We split your costs into materials bought up front, materials bought as the job goes, payroll and other weekly costs, and assume they're paid in the week they happen. We assume you bill for the work completed (evenly across the job, unless you change it) at each billing date, and that the customer pays the billed amount, less retainage, on your stated terms. Retainage comes back the set number of days after the job ends. The running total is your cash position on the job each week.
It doesn't include your overhead, other jobs, change orders, or supplier terms that let you pay for materials later. If you get net 30 from your supplier, shift the up-front materials later and run it again.
The default numbers are the worked example on our electrical contractors page: a $480,000, 16-week scope that peaks at about $306,000 in week 10.
Ways contractors close a gap (and what each costs)
- Bill for stored materials if your contract allows it. Free, but needs paperwork and GC approval.
- Supplier terms or joint checks. Net 30–60 from your supplier moves the material cost closer to your payment.
- Negotiate a mobilization payment or shorter terms before you sign. Rare, but worth asking.
- A bank line of credit. Usually the lowest cost if you qualify.
- Invoice factoring or a contract-specific line. Built around specific invoices or contracts.
- A revenue-based advance. Repaid from deposits; typically costs more than a bank line, but is often available to businesses a bank won't approve as quickly. Best for short, specific gaps when deposits are steady.
Compare them in detail: cash advance vs line of credit vs factoring. For a step-by-step plan for payroll gaps, read how to make payroll while you wait on a draw.
Download the blank worksheet
Prefer paper, or want to map several jobs at once? The blank cash-gap worksheet (PDF) has the same inputs and a 26-week grid. No email needed.
Talk it through with us
If the gap is real and the job is solid, tell us about it. We'll tell you honestly whether our funding fits, or whether something else would serve you better.